NOTICE OF COMPLETION AND FINAL ACCEPTANCE

In accordance with the provisions of paragraph 16-6-116, title 16, Chapter 6, Wyoming Statutes, 1982 Republished Edition, Notice is hereby given that TIMBERLINE SERVICES, INC, PO Box 867, Sundance, WY 82729-0867, as Contractor, has completed the SUNDANCE WEST STORAGE TANK PROJECT in accordance with all plans and specifications.

In accordance with the provisions of paragraph 15-1-113 (h) all persons having claims for labor and material furnished the contractor shall present them to the City of Sundance prior to the date specified for final payment.

Final inspection and acceptance thereof having been made, final payment is now due the Contractor in accordance with the terms of the contract.

Said final payment will be made on SEPTEMBER 8, 2021, said date being the 41st day after the first publication of the notice.

THE CITY OF SUNDANCE, WYOMING

By: Paul Brooks, Mayor

By: Kathy A. Lenz, Clerk Treasurer

City of Sundance

Publish: July 29, August 5 and 12, 2021

 
 